Okeechobee RNG Facility
Converting landfill gas into pipeline-grade renewable natural gas to power homes and businesses across Florida through innovative engineering and construction excellence.
Project Overview
At the Okeechobee Renewable Natural Gas (RNG) facility in Okeechobee County, Florida, United Group Services (UGS) played a key role in advancing the region’s clean-energy infrastructure — converting landfill gas into pipeline-grade renewable natural gas to power homes and businesses across the state.
Working directly for a leading national waste and environmental services company, UGS delivered fabrication, installation, and construction management for the facility’s mechanical and structural systems. This project is part of a partnership spanning over a decade, during which UGS has delivered a range of projects across the client’s operations, with a growing portfolio of RNG facilities in recent years as demand has accelerated — built on trust, safety, and precision execution.
The Challenge
Although the Okeechobee facility followed a familiar RNG design model, the project faced several early challenges that required expertise and adaptability:
-
Site Access Issues
Infrastructure delays restricted heavy equipment mobilization and foundation work
-
Tight Schedule
Required completion within original target date despite early obstacles
-
Environmental Compliance
Active landfill operations required careful planning to minimize impact
Drawing from its deep experience in the renewable gas sector, UGS maintained schedule integrity and overcame site delays through proactive planning, prefabrication, and continuous coordination among multiple teams.
Our Solution
UGS approached the Okeechobee project with its proven bid–buy–build model, combining early preconstruction planning, modular fabrication, and disciplined project controls.
Strategic Planning & Prefabrication
UGS’s planning department vetted all design drawings for potential clashes and field constraints before mobilization. The team prefabricated nearly all major system components off-site to accelerate installation and reduce field exposure:
This pre-planning and prefabrication effort ensured the project remained on track — even with restricted early-stage access.
Execution and Coordination
Once the site was released for construction, UGS:
Safety and Quality
Throughout construction, UGS upheld its strong culture of safety, quality, and accountability:
By maintaining focus and communication, the UGS team overcame initial site delays and still met the original project completion date, a testament to the company’s disciplined approach and reliable execution.
Project Services Provided
-
Piping fabrication and installation for gas, air, and water systems
-
Structural steel fabrication and erection (pipe racks and supports)
-
Equipment setting and alignment
-
Instrumentation and gas sampling tubing installation
-
Insulation installation for piping and vessels
-
Preconstruction planning, modeling, and project controls
-
On-site safety and quality management
Results & Impact
Despite early site restrictions, UGS completed its full scope on schedule and within budget, supporting a major renewable energy initiative that will help power thousands of homes across Florida.
The Okeechobee RNG Facility captures methane gas from landfill decomposition and converts it into renewable natural gas, thus reducing harmful emissions while creating a sustainable energy source for the community.
By leveraging extensive prefabrication and field coordination, UGS minimized on-site time, lowered costs, and maintained an impeccable safety record. The result: a successful, zero-incident project delivered to exacting quality standards.
People Who Made It Happen
Gary Clarke
Senior Account Manager, RNG Division
Gary led the project from bidding through completion and has provided long-term leadership across UGS’s RNG portfolio, continuing to support and strengthen the client partnership.
Field Leadership & Crew
26-28 Skilled Professionals
Our crew included welders, pipefitters, and insulators who delivered the work safely and efficiently, embodying UGS’s values of teamwork and precision.
Key Takeaways
-
Prefabrication
Significantly reduces cost, schedule, and field exposure.
-
Early planning and quality control
Ensure seamless execution even amid site delays.
-
Consistent safety culture
Produces repeatable, zero-incident results.
-
Long-term partnerships
Built on reliability and performance, this partnership has supported the delivery of an increasing number of RNG facilities in recent years and continues to drive sustainable growth.
About the Program
United Group Services has maintained a trusted partnership with this client for over a decade. In recent years, as the client experienced a surge in market demand, UGS has completed an average of five RNG facilities annually to support their growth. Each project reflects UGS’s commitment to advancing cleaner, more sustainable energy infrastructure while delivering consistent results across every scope and site.