Medley RNG Facility
Transforming landfill methane into pipeline-quality renewable natural gas through strategic prefabrication, disciplined execution, and innovative construction solutions within one of the most space-constrained RNG facilities in Florida.
Project Overview
At the Medley Renewable Natural Gas (RNG) Facility in Medley, Florida, United Group Services (UGS) helped deliver critical infrastructure that transforms landfill methane into pipeline-quality renewable natural gas. Constructed within a highly constrained site footprint, the project required disciplined planning, precise logistics, and seamless coordination across multiple trades to maintain schedule and execution efficiency.
As part of UGS’s growing portfolio of renewable gas facilities, the Medley project showcased the company’s ability to adapt construction strategies to meet unique field conditions. Through advanced prefabrication, detailed planning, and strong field leadership, UGS successfully delivered mechanical and structural systems while overcoming some of the most restrictive site conditions in its RNG program.
The Challenge
Unlike many large industrial construction projects, the Medley facility offered very limited space for material storage, equipment staging, and active construction work. The compact footprint created logistical challenges that required careful sequencing and elevated coordination between trades.
Key project challenges included:
-
Restricted Site Access
Limited working space required UGS to establish and manage an off-site laydown yard for prefabricated materials, equipment, and steel deliveries. This added complexity to daily operations and required exact coordination to ensure crews received materials precisely when needed.
-
Congested Work Environment
Multiple contractors performed underground and civil work simultaneously within a constrained footprint, increasing the importance of schedule coordination and installation sequencing.
-
Equipment Setting Contraints
Traditional crane placement strategies would have disrupted site access and underground progress. To maintain productivity, UGS reevaluated the installation approach and engineered an alternative lifting strategy that minimized site interference.
Despite these challenges, the project team maintained momentum through proactive communication, detailed planning, and flexible execution.
Our Solution
To maximize efficiency in a restricted environment, UGS implemented a highly coordinated planning process before mobilization. Construction sequencing, staging plans, and field logistics were carefully developed to minimize congestion and maintain safe working conditions.
Precision Planning & Logistics Management
A critical contributor to the project’s success was Clayton Beiser, Planner, whose efforts helped make prefabrication a major advantage for the Medley team.
Clayton led:
- Detailed layout development
- Field verification and dimensional validation
- Real-time refinement of isometric drawings for shop fabrication
This level of planning enabled UGS to fabricate with greater certainty, reduce field modifications, and maintain installation efficiency despite tight working conditions.
As a result, UGS achieved:
- Approximately 16,000 feet of carbon-steel and stainless-steel piping fabricated and installed
- 94 tons of structural steel erected for pipe racks and support systems
- Approximately 98% piping prefabrication, significantly reducing field labor and installation complexity
Execution & Field Coordination
Given the site’s tight footprint, UGS adopted a unique lifting strategy to avoid disrupting ongoing underground construction activities.
Rather than utilizing multiple hydraulic cranes throughout the project site, the team strategically deployed an MLC300 crawler crane positioned from one side of the facility to receive, offload, and place major equipment.
Through this coordinated approach, UGS successfully:
- Received, offloaded, and installed 71 pieces of equipment totaling approximately 788 tons
- Installed all required insulation for piping and vessels
- Completed instrumentation and gas sampling tubing installation for system monitoring and operational performance
- Coordinated daily with project stakeholders to maintain alignment across disciplines and preserve schedule integrity
Safety & Quality
Throughout construction, UGS maintained its commitment to disciplined execution, workforce accountability, and field safety.
Project performance included:
- Zero incidents or accidents during construction
- Daily safety huddles focused on hazard awareness and coordination
- Ongoing quality inspections to verify weld integrity and installation accuracy
Despite early site challenges and logistical restrictions, UGS maintained the original completion schedule, demonstrating the effectiveness of its planning process and field leadership.
Project Services Provided
-
Piping fabrication and installation for gas, air, and condensate systems
-
Structural steel fabrication and erection (pipe racks and supports)
-
Receive, off load and set equipment
-
Instrumentation and gas sampling tubing installation
-
Insulation installation for piping and vessels
-
Construction planning and field logistics coordination
-
Project controls and schedule management
-
Safety and quality oversight
Results & Impact
The Medley RNG Facility demonstrates how disciplined planning and execution can overcome significant logistical constraints without sacrificing schedule, quality, or safety.
By combining high-level prefabrication with thoughtful field coordination, UGS minimized installation congestion, reduced field exposure hours, and maintained productivity in a challenging environment.
The completed facility now converts landfill methane into renewable natural gas, helping reduce emissions while supporting long-term sustainable energy production for the region.
Most importantly, UGS delivered the project:
- On schedule
- With zero safety incidents
- While successfully navigating one of the most space-constrained RNG projects in its portfolio
People Who Made It Happen
Gary Clarke
Senior Account Manager, RNG Division
Led project planning, procurement, and execution, continuing UGS’s long-standing leadership in renewable natural gas infrastructure.
Field Leadership & Crew
26-28 Skilled Professionals
UGS’s field team maintained a strong culture of accountability, craftsmanship, and teamwork, safely delivering complex work in a highly constrained environment.
Key Takeaways
-
Strong planning and logistics
Helped with overcoming space constraints.
-
High-level prefabrication
Improved efficiency and reduced field labor.
-
Creative execution strategies
Protected schedules in congested environments.
-
Safety and quality
Remained foundational to successful project delivery.
-
Experience in RNG infrastructure
Enabled confident execution under challenging conditions.
About the Program
The Medley facility is one of 14 Renewable Natural Gas projects completed by UGS with this client since 2018. From landfill gas recovery to pipeline-quality RNG infrastructure, UGS continues to help clients advance cleaner energy solutions through disciplined industrial construction and proven field execution.